Question Regarding Cost per Edging ( 2 x Year )

PostPosted: Fri Mar 14, 2014 2:40 pm
by DSHAadminMGT
A Contractor asked what figure should be listed in the space provided on page 19 under
Cost per Edging ( 2 x Year ). They wanted to know if it should be a total for both edgings
or per occurrence.

PostPosted: Fri Mar 14, 2014 2:48 pm
by DSHAadminMGT
Page 19 of the RFP packet indicates that the Cost per Edging
should be listed. Contractors may write the word total next
to the dollar value if the figure listed is the total for two
(2) edgings. If the figure listed is per edging then the
Contractor may write the words per edging, next to the dollar
value. DSHA may request clarification from proposers if there
appears to be any concerns regarding responses given in this field.